Data centers are turning to old jet engines as the wait for power grows
AI-assisted digest, checked against the original source before publishing. How we work
AI data centers are bypassing grid queues by converting retired jet engines into on-site power.
Speed is the main attraction. Rystad Energy analyst Audun Martinsen told the Times that jet-powered units let operators get a data center running in about 24 months. By contrast, the International Energy Agency estimates connecting 100 megawatts to the grid in Northern Virginia takes roughly seven years, with most capacity expected online by 2031, a Mitsubishi Power executive told Bloomberg.
Delays are already costing operators contracts. Microsoft withdrew as anchor customer for Nscale's data center in Loughton, England, after the local utility said sufficient power would not be available until the early-to-mid 2030s. Meanwhile, the Trump administration is encouraging data centers to generate their own electricity, adding further pressure toward self-supply.
Adoption is spreading quickly. xAI has installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis, the Times reported, citing state permits and satellite imagery; the units come from ProEnergy, which rebuilds a GE engine commonly used on Boeing jets. OpenAI followed with gas turbines at its first Stargate site in Abilene, Texas, in 2025, and Crusoe, the Denver startup building that campus, ordered 13 ProEnergy units in April. In September, Crusoe abandoned a $1.25 billion deal to buy 29 natural gas turbines from Boom Supersonic, though it said it still plans to use turbines.
The trade-offs are real. Converted engines are less efficient, pollute more, and require more units for equivalent output than turbines designed for conventional gas plants, the Times noted. Some experts believe efficiency and environmental concerns could grow in importance within a year or two, potentially making jet-engine power a short-lived solution.
What to watch: whether the 24-month advantage survives as emissions scrutiny and fuel costs tighten, how many operators follow xAI and Crusoe before turbine supply and grid queues ease, and whether policy support for on-site generation persists — or whether stranded, underused converted units become the next write-down for AI infrastructure builders.
Key facts
- • Grid connection for 100 MW in Northern Virginia takes about seven years.
- • Jet-engine units can bring a data center online in 24 months.
- • xAI installed eight converted jet-engine turbines in Mississippi for Colossus 2.
- • Crusoe ordered 13 ProEnergy converted units in April for Abilene.
- • Crusoe walked away from a $1.25 billion Boom Supersonic turbine deal.
Why it matters
Builders facing multi-year grid queues can now buy time with rapidly deployable on-site generation, but at the cost of higher emissions and lower efficiency that may invite future scrutiny or retrofit expenses. Watch for these units becoming stranded assets if turbine supply and grid capacity catch up within the next one to two years.
Spotted an error? Send a correction.